Project management and construction engineering quizz: Cost Control

See other solutions of this package or all our solution manuals.

Question

If BAC for a work package is $10,000 and EV = $4,000 then the work package is:
* 80% complete
* 40% complete
* 120% complete
* 100% complete

Solution