Project management and construction engineering quizz: Cost Control
See
other solutions of this package
or
all our solution manuals
.
Question
If BAC for a work package is $10,000 and EV = $4,000 then the work package is:
* 80% complete
* 40% complete
* 120% complete
* 100% complete
Solution
Only members can see full solutions. Please
log in
or
register
.