Solution of Soil Compaction Check Via The Voids Ratio
Articles > Solution of Soil Compaction Check Via The Voids RatioQuestion:
A contractor has compacted the base course for a new road and found that the mean value of the test samples shows w = 14.6%, Gs = 2.81, and γ = 18.2 kN/m3. The specifications require that e < 0.80. Has the contractor complied with the specifications?
Solution:
For formulas of soil phase relationships read Soil Phase Relationships article.
Thus
Yes, the contractor has complied.