Project management and construction engineering quizz: Cost Control
Question
Find the synonymous of following terms from the second list* Planned Value (PV)
* Budget Cost for Work Performed (BCWP)
* Actual Cost (AC)
* Estimate To Complete (ETC)
* Estimate At Completion (EAC)
* Actual Cost for Work Performed (ACWP)
* Budget At Completion (BAC)
* Earned Value (EV)
* Budgeted Cost for Work Scheduled (BCWS)