Project management and construction engineering quizz: Scheduling Networks

See other solutions of this package or all our solution manuals.

Question

You have an activity where the early start is week 6, the early finish is week 10, the latest start is week 14, and the latest finish is week 18. The float in this activity is:
* 18 weeks
* 4 weeks
* 5 weeks
* 8 weeks

Solution

Only members can see full solutions. Please log in or register.