Project management and construction engineering quizz: Scheduling Networks
Question
You have an activity where the early start is week 6, the early finish is week 10, the latest start is week 14, and the latest finish is week 18. The float in this activity is:* 18 weeks
* 4 weeks
* 5 weeks
* 8 weeks