Project management and construction engineering quizz: Scheduling Networks

See other solutions of this package or all our solution manuals.

Question

A network based schedule has four paths, with the following durations 7, 8, 9, and 10 weeks. If the 10 week path is compressed to 8 weeks, then:
* We now have two critical paths
* The 9 week path is now the critical path
* Only the 7 week path has float
* Not enough information is provided to make a decision

Solution